Project Description

Cidon were appointed by Code Students to undertake the remediation, enabling and substructure works package for a landmark co-living development on Wellington Street, in Sheffield city centre.
The work scope included:
- Removal of all existing concrete structures in the ground.
- Bulk muck shift
- Consolidation works of old mine workings and entries which involved drilling and pumping over 1M litres of grout within the site boundary.
- Vibration monitoring.
- Installation of pile mats.
- Installation of contiguous pile wall and bearing piles.
- Construction of capping beam, pile caps and bases including drainage and connections into the main carriageway.
Unique Features
.png)
- Logistically challenging city centre location.
- Risk of UXO
- Extensive network of old mine workings and entries across the site.